In project scheduling, what does the term 'Lead Time' mean?
Continue
Advertisement
💡
Hint
…
⚖️
50-50
…
👥
Audience
…
A
The time it takes to cure poured concrete
B
The duration between placing an order for materials and their delivery to the site
C
The length of the architectural design phase
D
The total daily hours worked by the lead foreman